The closures are required for the safety of the public and workforce while carriageway works are undertaken by Walker Construction (UK) Ltd.

 

Start works on Monday 8th August 2022

  • Close Old Kent Road junction Monday 8th August 2022 – Sunday 11th September (TTRO application included)
  • With signal control, undertake drainage and kerbing works in the Old Kent Road/ Network Rail junction (planned 2 weeks)
  • Install Road Closure on Sunday 21st August for 1x full day to undertake carriageway planning & re-surfacing
  • Following road closure, then re-install signals to undertake imprint surfacing (3 weeks needed)
  • Lift signals and Old Kent Road closure by COP Sunday 11th September
  • Monday 12th September, Install signals off peak hours at Church Road/ Warrington Rd junction to undertake kerbing remedials and footway surfacing (1x week work required)